Project construction program
Project Installation?Program
1. Site manager to prepare crane/forklift equipment and installation tools (cable reels. wrenches. electric wrenches. etc.) in advance.
2. After the equipment arrives on the site. the installation manager arranges the forklift in readiness to unload the conveying equipment. Then use the forklift to move the conveyor equipment to the planned location for the positioning.
3. Installing the fence and connecting the power line
Note: Installation of the fence requires the use of an electric hammer drill. Precaution to the customer for noise. Connecting the power line may cause fire. so the working area needs to be equipped with fire extinguishers. Apply for the hot work permit file.
4. commissioning and training. It is suggested for the user to arrange 2-3 people in advance to learn the operation procedure of the equipment. the maintenance of the equipment and troubleshooting.
Installation precautions?
1. Lifting equipment MUST avoid high-voltage lines. Pull a warning line.
2. Before starting a hot work. you must apply for a hot work permit file. the welding operator must be a licensed.
3. In the workshop get permission before starting hot works.
4. In the installation site should follow the relevant provisions of the workshop.
5. Installation workers must wear helmets and other labor protective gears at the installation site.
6. Use the warning tape to make a good enclosure warning in the installation site.
7. Need to be equipped with fire extinguishers.
8. Check the installation scope before starting the hot work. if there are flammable and explosive materials. they need to be isolated or removed 15m far away at least.
9. Working at higher position higher than 2 meters. not only wearing the basic labor insurance products. but also must wearing a safety belt. safety belt need to be hung at higher position on a strong object. A assistant needs to supervise on the floor.
10. Electricity in the workshop must be accessed through the maintenance box with MCB unit with leakage protection.
11. the use of welding machines. sanders. drills and other tools. you need to follow the use of tools related to the norms.
12. When welding. the ground wire of the welding machine must be clamped on the hot parts and within 0.5 meters from the welding point.
13. Clean the installation site. and clean up the waste materials and garbage during the installation in time every day.
Project Team Structure and Responsibilities
The company is equipped with: safety staff. special operations. electricians. welding and other project personnel. the project manager is responsible for the entire project. and other personnel are responsible for daily feedback to the company in a timely manner to the installation progress and the content of the day's work. and weekly summary of the work.
Duties of project installation and commissioning personnel:
1. in accordance with the company's business objectives. the implementation of the company or the project manager's instructions to do a good job in the installation site production plan. safety. civilized production and its coordination and management.
2. the implementation of the company's quality policy and quality objectives. to ensure the completion of the installation technology and work tasks.?
3. organization and management of installation activities. responsible for the quality of its work. Adhere to the "careful installation. quality service" to stop illegal work. to ensure that the quality of the project is reliable and stable.
4. ?Participate in the evaluation of quality problems and put forward treatment methods.
5. Responsible for on-site quality inspection and confirmation.
6. ?Ensure that the installation quality is 100% in line with the contract requirements.
Regulations and Norms of Installation
1. Installation drawings and design specifications
2. "Code for construction of field equipment. industrial pipe welding engineering" ?GB50236-2011
3. "Specification for the Installation and Acceptance of Electric Installation Engineering Cable Line " GB50168-2006
4. "Unified Standard for construction Quality Acceptance of Industrial Installation Engineering " GB50252-2010
5. "Safety Technical Specification for Temporary Electricity on Installation Sites " ?JGJ46-2005