Equipment Installation Program
Equipment Installation Program
1. packing machine installation, conveyor installation
2. test running
The main power supply is wired correctly, each motor (packing machine, conveyor) rotation is correct, and each action in jogging mode is correct,no alarm in active.
3. Single packing machine commissioning
It is suggested that the customer to arrange one or two operators to join the commissioning, learning the operation, parameters adjusting, and troubleshooting.
4. Training for equipment operators (refer to the instruction manual)
(1) Operation and use of the equipment.
(2) Maintenance and spare parts management.
(3) machine cleaning, and the lubrication.
(4) It is important to highlight the function of emergency stop button and the cabinet main switch, they are supposed to be active only in the event of an abnormal emergency, and not to be used for the normal stopping of the equipment.
(5) The safety regulation is to declared priority on training, including the safety of equipment and human. In the operation of the machine, parts replacement, and maintenance, LOTO must be carried out in the case of stopping the machine.